RHD Operational Procedure Planning and Maintenance Wing |
|
Planning and Programming - Planning Division |
|
OP/PPC/2.1 - Preparation of Planning Commission Form - II (PC-II) |
|
Purpose and Scope :
This procedure describes the process for preparing the Preliminary Project Concept Paper in Planning Commission Form-II (PC-II) for preparing a report on Feasibility Study of any Project to be conducted through GOB fund. |
|
Definitions :
Planning Commission Form-II (PC-II) is a proposal in a concise form that is submitted to MoC for project approval and inclusion in the Annual Development Programme (ADP). A PC-II is required for any Feasibility Study Project to be conducted through GoB fund. It should include a brief description of the project, scope of work, scope of consulting services, ToR, total cost of consulting services, etc, in the prescribed format of PC-II.
|
|
Responsibility :
Executive Engineer - Planning Division (EE-PD) is responsible for collecting all required data and organising and preparing the draft PC-II.
Superintending Engineer - Planning & Programming Circle (SE-PPC) is responsible for reviewing the PC-II and making recommendation for approval of the draft PC-II to the Additional Chief Engineer - Planning & Maintenance Wing.
Additional Chief Engineer - Planning & Maintenance Wing (ACE-PMW) gives the final clearance from the Wings point of view and submits the final draft of the PC-II to the Chief Engineer for his signature along with other signatories responsible for preparation of the PC-II and for submission to the MoC.
Additional Chief Engineers - Field Zone/Bridge Management Wing/Other Wings are responsible for ensuring that his subordinate officers submit the required information/draft PC-II to the SE-Planning & Programming Circle precisely and in time. |
|
Method :
4.1 PREPARATION OF THE DRAFT PC-II
The Superintending Engineer - Planning & Programming Circle receives the data related to the project in the PC-II format from a number of sources:
· The main source of information is from the field offices for mainly road projects. Following necessary surveys, the concerned field offices supply the required data generally in the PC-II format as and when instructed by the higher authority.
· For bridge projects, the Additional CE, Bridge Management Wing with the assistance of his SE, Planning & Data Circle prepares the draft PC-II.
The Executive Engineer - Planning Divisions scrutinises the draft PC-II and may request further information, or clarification of the data. He also ensures that the PC-II is in the prescribed format of the Planning Commission.
4.2 FINAL DRAFT PC-II
The Executive Engineer - Planning Divisions submits the draft PC-II to the Superintending Engineer - Planning & Programming Circle, who reviews the submission. He may ask for additional information or clarification.
When the SE P&P is satisfied, that the PC-II is accurate and contains all of the necessary information, it is reviewed by the Additional Chief Engineer - Planning & Maintenance Wing and submitted to the Chief Engineer as a final draft for his signature.
4.3 SUBMISSION TO THE MINISTRY OF COMMUNICATIONS
When the Chief Engineer has signed the PC-II along with other signatories concerned with the preparation of the PC-II, it is submitted to the Ministry of Communications by the Superintending Engineer - Planning & Programming Circle on behalf of the CE-RHD for approval and inclusion of the project in the ADP. |
|
References :
Planning Commission Guidelines published by Planning Commission
5 year Development Plan published by Planning Commission |
|
Procedure Flowchart :
The procedure flowchart for this procedure is detailed below - |
|
|
|
|
|
|
|