List of ongoing works on the road ( N517 )
Fund Source   Contract no.   St. Date   Duration   Type of work  Start location End location  Res.Division 
           LRP   Offset  Chainage      LRP   Offset  Chainage      
 Development  06-SE/RRC/2010-2011.  7-Feb-2011  547 Days  Carpeting  LRPS  0 0     LRP002  591 3     Rangpur, (Division Office) 
 Development  01-ACE/RGZ/2013-2014.  15-May-2014  365 Days  Carpeting  LRPS  0 0     LRP002  0 2.409     Rangpur, (Division Office) 
 Revenue Periodic Roads  07-EE/RRD/2006-2007. Lot no. 01  11-Jun-2007  20 Days  Carpeting  LRPS  700 0.7     LRP002  -209 2.2     Rangpur, (Division Office) 
 Development  08-SE/RRC/2010-2011.  20-Apr-2011  547 Days  Pavement  LRP002  0 2.409     LRP004  0 4.391     Rangpur, (Division Office) 
 Revenue Periodic Roads  06-EE/RRD/2005-2006, Lot No. 01(One).  14-May-2006  35 Days  SBST  LRP002  0 2.409     LRP002  250 2.659     Rangpur, (Division Office) 
 Revenue  eGP no. 15/RHD/EE/Rang/2015-2016 (ID-45870)  31-Mar-2016  60 Days  Carpeting  LRPS  2700 2.7     LRPS  3500 3.5     Rangpur, (Division Office) 
 Development  E-gp no. 01/RHD/SE/RANG/2014-2015 (ID no. 15916)  19-Feb-2015  270 Days  Carpeting  LRP002  591 3     LRPE  0 8.242     Rangpur, (Division Office) 
 Development  03-ACE/RGZ/2013-14*  28-May-2014  398 Days  Carpeting  LRP002  682 3.091     LRP004  666 5.057     Rangpur, (Division Office) 
 Revenue Others  05-EE/RRD/2007-2008. Lot no. 05(Five).  16-Mar-2008  45 Days  Carpeting  LRP002  976 3.385     LRP002  1501 3.91     Rangpur, (Division Office) 
 Revenue  PMP-2008-09/17/DBST & Overlay.  2-Apr-2009  360 Days  Overlay  LRP002  982 3.391     LRP007  452 7.831     Rangpur, (Division Office) 
 Development  03-ACE/RGZ/2013-2014.  28-May-2014  121 Days  Carpeting  LRP004  0 4.391     LRP006  0 6.389     Rangpur, (Division Office) 
 Revenue Others  05-EE/RRD/2007-2008. Lot no. 04(Four).  18-Mar-2008  45 Days  Carpeting  LRP004  229 4.62     LRP004  644 5.035     Rangpur, (Division Office) 
 Revenue Periodic Roads  07-EE/RRD/2006-2007. Lot no. 04(Four)  10-Jun-2007  30 Days  Carpeting  LRP006  -1354 5.035     LRP006  554 6.943     Rangpur, (Division Office) 
 Development  10-EE/RRD/2011-2012.  19-Jul-2012  455 Days  Pavement  LRP004  1109 5.5     LRPE  0 8.242     Rangpur, (Division Office) 
 Revenue  08-EE/RRD/2009-2010.  15-Jun-2010  270 Days  Surfacing  LRP006  71 6.46     LRPE  0 8.242     Rangpur, (Division Office) 
 
 Note: The on going work list is gathered from Central Management System (CMS) running in the field divisions and the information is updated once in a month at RHD head office. This information is largely depended on how the work is defined in CMS and will not include any contract that is not properly defined by field division