| List of ongoing works on the road ( N514 ) |
Fund Source  |
Contract no.  |
St. Date  |
Duration  |
Type of work  |
Start location |
End location |
Res.Division  |
| |
|
|
|
|
LRP  |
Offset  |
Chainage |
LRP  |
Offset  |
Chainage |
|
| Revenue PMP |
PMP 2007-08/01/Overlay & DBST |
17-Feb-2008 |
683 Days |
Overlay |
LRPS |
|
0 |
LRPS |
900 |
0.9 |
Bogura, (Division Office) |
| Revenue |
eGP-38/EE/BRD/2016-2017 (ID No. 82888) |
17-May-2017 |
29 Days |
Carpeting |
LRPS |
0 |
0 |
LRP005 |
0 |
5 |
Bogura, (Division Office) |
| Revenue |
eGP-39/EE/BRD/2016-2017 (ID No. 94403) |
17-May-2017 |
29 Days |
Carpeting |
LRPS |
0 |
0 |
LRPE |
0 |
8.67 |
Bogura, (Division Office) |
| Development |
67-EE/BRD/2007-2008 |
3-Apr-2008 |
90 Days |
Pavement |
LRPS |
200 |
0.2 |
LRP005 |
3500 |
8.5 |
Bogura, (Division Office) |
| Development |
03-EE/BRD/2005-2006, Lot No. 03/01 |
15-Jun-2006 |
30 Days |
Carpeting |
LRPS |
3500 |
3.5 |
LRPS |
7319 |
7.319 |
Bogura, (Division Office) |
| Development |
BRD-38-EE/2008-2009 |
22-Feb-2009 |
30 Days |
Overlay |
LRPS |
3750 |
3.75 |
LRPS |
3800 |
3.8 |
Bogura, (Division Office) |
| Revenue |
eGP-29/EE/BRD/2016-2017 (ID-81231) |
16-Apr-2017 |
29 Days |
Carpeting |
LRP005 |
0 |
5 |
LRPE |
0 |
8.67 |
Bogura, (Division Office) |
| Revenue |
10-EE/BRD/2015-2016 |
12-Jan-2016 |
30 Days |
Carpeting |
LRP005 |
0 |
5 |
LRPE |
0 |
8.67 |
Bogura, (Division Office) |
| Revenue |
11-EE/BRD/2014-15 |
23-Mar-2015 |
45 Days |
Surfacing |
LRP005 |
0 |
5 |
LRPE |
0 |
8.67 |
Bogura, (Division Office) |
| Revenue |
31-EE/BRD/2012-13 |
12-Mar-2013 |
30 Days |
Surfacing |
LRP005 |
250 |
5.25 |
LRP005 |
2500 |
7.5 |
Bogura, (Division Office) |
| Revenue Others |
06-SE/BRC/2007-2008 |
14-May-2008 |
45 Days |
Carpeting |
LRP005 |
658 |
5.658 |
LRP005 |
2680 |
7.68 |
Bogura, (Division Office) |
| Revenue Others |
06-SE/BRC/2007-2008 |
14-May-2008 |
45 Days |
Carpeting |
LRP005 |
3020 |
8.02 |
LRP005 |
3550 |
8.55 |
Bogura, (Division Office) |