| List of ongoing works on the road ( R685 ) |
Fund Source  |
Contract no.  |
St. Date  |
Duration  |
Type of work  |
Start location |
End location |
Res.Division  |
| |
|
|
|
|
LRP  |
Offset  |
Chainage |
LRP  |
Offset  |
Chainage |
|
| Revenue |
e-GP/RAZ/PMP (Road)/04/2014-2015 |
3-Nov-2014 |
180 Days |
Overlay |
LRPS |
0 |
0 |
LRP032 |
429 |
31.2 |
Rajshahi, (Division Office) |
| Revenue |
RFQ No.46-RRD/2012-2013. |
5-May-2013 |
15 Days |
Carpeting |
LRPS |
0 |
0 |
LRPS |
150 |
0.15 |
Rajshahi, (Division Office) |
| Revenue |
RFQ No. 03-SDE-1/2010-11. |
1-Jun-2011 |
15 Days |
Road Embankment |
LRP002 |
864 |
1.728 |
LRP002 |
1664 |
2.528 |
Rajshahi, (Division Office) |
| Revenue |
09-RRD/2011-2012(Lot No 05) |
21-Jun-2012 |
60 Days |
Surfacing |
LRP005 |
336 |
4.2 |
LRP005 |
936 |
4.8 |
Rajshahi, (Division Office) |
| Revenue |
RFQ No. 02-SDE-1/2010-11(Lot no.02). |
1-Sep-2011 |
15 Days |
Carpeting |
LRP004 |
2865 |
5.73 |
LRP004 |
4759 |
7.624 |
Rajshahi, (Division Office) |
| Revenue |
06-RRD/2011-2012Lot No 02) |
7-Jun-2012 |
60 Days |
Surfacing |
LRP010 |
447 |
9.294 |
LRP011 |
47 |
9.894 |
Rajshahi, (Division Office) |
| Revenue |
06-RRD/2011-2012Lot No 02) |
7-Jun-2012 |
60 Days |
Surfacing |
LRP011 |
847 |
10.694 |
LRP012 |
647 |
11.492 |
Rajshahi, (Division Office) |
| Revenue |
DPM No.10-RRD/2010-2011. |
2-Jun-2011 |
5 Days |
Road Embankment |
LRP024 |
500 |
23.306 |
LRP024 |
750 |
23.556 |
Rajshahi, (Division Office) |
| Revenue |
DMP No.14-RRD/2010-2011. |
2-Jun-2011 |
5 Days |
Road Embankment |
LRP025 |
200 |
24.003 |
LRP025 |
900 |
24.703 |
Rajshahi, (Division Office) |
| Revenue |
DPM No.13-RRD/2010-2011. |
2-Jun-2011 |
5 Days |
Road Embankment |
LRP027 |
300 |
26.085 |
LRP027 |
950 |
26.735 |
Rajshahi, (Division Office) |
| Revenue |
RFQ No.30-RRD/2012-2013. |
10-Apr-2013 |
15 Days |
Road Embankment |
LRP030 |
1217 |
30 |
LRP031 |
410 |
30.187 |
Rajshahi, (Division Office) |
| Revenue Periodic Roads |
Quotation 09-NRD/2005-2006 (Lot No. 09/09) |
3-Jan-2006 |
15 Days |
Pavement |
LRP033 |
400 |
32.173 |
LRP033 |
800 |
32.573 |
Naogaon, (Division Office) |
| Revenue Others |
Tender 06-NRD/2006-2007 (Lot No. 06/04) |
21-Dec-2006 |
35 Days |
Carpeting |
LRP034 |
113 |
32.9 |
LRP035 |
14 |
33.8 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 19-NRD/2005-2006 (Lot No. 19/09) |
2-Jul-2006 |
15 Days |
Pavement |
LRP034 |
120 |
32.907 |
LRP034 |
190 |
32.977 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 04-NRD/2005-2006 (Lot No. 04/01) |
18-Jun-2006 |
25 Days |
Pavement |
LRP034 |
200 |
32.987 |
LRP034 |
500 |
33.287 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 12-NRD/2005-2006 (Lot No. 12/01) |
14-Jun-2006 |
25 Days |
Pavement |
LRP034 |
200 |
32.987 |
LRP034 |
400 |
33.187 |
Naogaon, (Division Office) |
| Revenue |
08/e-GP/NRD/2015-2016 |
30-Dec-2015 |
30 Days |
Carpeting |
LRP003 |
32000 |
33.86 |
LRP034 |
34550 |
67.337 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 19-NRD/2005-2006 (Lot No. 19/09) |
2-Jul-2006 |
15 Days |
Pavement |
LRP035 |
150 |
33.936 |
LRP035 |
220 |
34.006 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 19_NRD/2005-2006 (Lot No. 19/09) |
2-Jul-2006 |
15 Days |
Pavement |
LRP035 |
200 |
33.986 |
LRP035 |
400 |
34.186 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 07-NRD/2006-2007 (Lot No. 07/4) |
16-Jan-2007 |
35 Days |
Carpeting |
LRP036 |
268 |
35.05 |
LRP036 |
1168 |
35.95 |
Naogaon, (Division Office) |
| Revenue Others |
Tender 06-NRD/2006-2007 (Lot No. 6/04) |
21-Dec-2006 |
251 Days |
Pavement |
LRP036 |
268 |
35.05 |
LRP037 |
161 |
35.95 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 19_NRD/2005-2006 (Lot No. 19/09) |
2-Jul-2006 |
15 Days |
Pavement |
LRP036 |
300 |
35.082 |
LRP036 |
500 |
35.282 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 19-NRD/2005-2006 (Lot No. 19/09) |
2-Jul-2006 |
15 Days |
Pavement |
LRP036 |
500 |
35.282 |
LRP036 |
700 |
35.482 |
Naogaon, (Division Office) |
| Deposit Works |
Quotation 04-NRD/2005-2006 (Lot No. 04/07) |
18-Jun-2006 |
15 Days |
Pavement |
LRP037 |
200 |
35.989 |
LRP037 |
500 |
36.289 |
Naogaon, (Division Office) |
| Revenue |
DPM 03-NRD/2010-2011 (Package-02) |
5-Apr-2011 |
7 Days |
Carpeting |
LRP037 |
211 |
36 |
LRP038 |
219 |
37 |
Naogaon, (Division Office) |
| Revenue |
Quotation 03-NRD/2011-2012 (Package-01) |
8-Jan-2012 |
7 Days |
Carpeting |
LRP037 |
350 |
36.139 |
LRP037 |
360 |
36.149 |
Naogaon, (Division Office) |
| Revenue |
DPM 04-NRD/2011-2012 (Package-07) |
24-Nov-2011 |
7 Days |
Pavement |
LRP037 |
400 |
36.189 |
LRP037 |
700 |
36.489 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 19_NRD/2005-2006 (Lot No. 19/09) |
2-Jul-2006 |
15 Days |
Pavement |
LRP037 |
500 |
36.289 |
LRP037 |
900 |
36.689 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 04-NRD/2005-2006 (Lot No. 04/01) |
18-Jun-2006 |
25 Days |
Pavement |
LRP038 |
100 |
36.881 |
LRP038 |
300 |
37.081 |
Naogaon, (Division Office) |
| Revenue |
LTM 01-NRD/2010-2011 (Package-06) |
14-Oct-2010 |
15 Days |
Carpeting |
LRP038 |
200 |
36.981 |
LRP038 |
600 |
37.381 |
Naogaon, (Division Office) |
| Deposit Works |
Quotation 10-NRD/2005-2006 (Lot No. 10/12) |
24-Aug-2006 |
15 Days |
Pavement |
LRP039 |
200 |
37.968 |
LRP039 |
500 |
38.268 |
Naogaon, (Division Office) |
| Revenue |
DPM 04-NRD/2011-2012 (Package-06) |
22-Nov-2011 |
7 Days |
Pavement |
LRP039 |
232 |
38 |
LRP039 |
500 |
38.268 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 20-NRD/2005-2006 (Lot No. 20/04) |
15-May-2006 |
15 Days |
Pavement |
LRP040 |
100 |
38.874 |
LRP040 |
300 |
39.074 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Quotation 10-NRD/2005-2006 (Lot No 10/12) |
24-Aug-2006 |
15 Days |
Pavement |
LRP040 |
100 |
38.874 |
LRP040 |
600 |
39.374 |
Naogaon, (Division Office) |
| Revenue |
DPM 05-NRD/2011-2012 (Package-03) |
26-Apr-2012 |
7 Days |
Road Embankment |
LRP040 |
400 |
39.174 |
LRP040 |
600 |
39.374 |
Naogaon, (Division Office) |
| Revenue |
DPM 04-NRD/2011-2012 (Package-05) |
22-Nov-2011 |
7 Days |
Pavement |
LRP040 |
570 |
39.344 |
LRP040 |
800 |
39.574 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 20-NRD/2005-2006 (Lot No. 20/04) |
15-May-2006 |
15 Days |
Pavement |
LRP041 |
200 |
39.977 |
LRP041 |
600 |
40.377 |
Naogaon, (Division Office) |
| Revenue |
Quotation 09-NRD/2005-2006(Lot No. 09/05) |
14-Dec-2005 |
7 Days |
Pavement |
LRP041 |
350 |
40.127 |
LRP041 |
500 |
40.277 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 24-NRD/2005-2006 (Lot No. 24/02) |
11-Jul-2006 |
25 Days |
Pavement |
LRP043 |
200 |
41.962 |
LRP043 |
500 |
42.262 |
Naogaon, (Division Office) |
| Revenue |
DPM 03-NRD/2010-2011 (Package-01) |
5-Apr-2011 |
7 Days |
Carpeting |
LRP043 |
238 |
42 |
LRP044 |
261 |
43 |
Naogaon, (Division Office) |
| Revenue |
DPM 05-NRD/2011-2012 (Package-04) |
26-Apr-2012 |
7 Days |
Carpeting |
LRP043 |
400 |
42.162 |
LRP043 |
600 |
42.362 |
Naogaon, (Division Office) |
| Deposit Works |
Quotation 04-NRD/2005-2006 (Lot No. 04/07) |
18-Jun-2006 |
15 Days |
Pavement |
LRP044 |
300 |
43.039 |
LRP044 |
500 |
43.239 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 38-NRD/2005-2006 (Lot No. 38/11) |
20-Sep-2006 |
15 Days |
Pavement |
LRP044 |
300 |
43.039 |
LRP044 |
700 |
43.439 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 24-NRD/2005-2006 (Lot No. 24/02) |
11-Jul-2006 |
25 Days |
Pavement |
LRP044 |
500 |
43.239 |
LRP044 |
800 |
43.539 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP045 |
0 |
43.762 |
LRP045 |
1000 |
44.762 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP045 |
0 |
43.762 |
LRP045 |
1000 |
44.762 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 38-NRD/2005-2006 (Lot No. 38/11) |
20-Sep-2006 |
15 Days |
Pavement |
LRP045 |
100 |
43.862 |
LRP045 |
600 |
44.362 |
Naogaon, (Division Office) |
| Revenue |
DPM-N 01-NRD/2012-2013 (Package-11) |
14-Aug-2012 |
7 Days |
Carpeting |
LRP045 |
420 |
44.182 |
LRP045 |
690 |
44.452 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 28-NRD/2005-2006 (Lot No. 28/03 |
13-Jul-2006 |
15 Days |
Road Embankment |
LRP046 |
0 |
44.758 |
LRP046 |
54 |
44.812 |
Naogaon, (Division Office) |
| Revenue |
DPM 03-NRD/2010-2011 (Package-03) |
5-Apr-2011 |
7 Days |
Carpeting |
LRP046 |
242 |
45 |
LRP047 |
249 |
46 |
Naogaon, (Division Office) |
| Revenue |
DPM-N 01-NRD/2012-2013 (Package-14) |
14-Aug-2012 |
7 Days |
Carpeting |
LRP046 |
350 |
45.108 |
LRP046 |
420 |
45.178 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 06-NRD/2006-2007 (Lot No. 06/05) |
14-Jan-2007 |
35 Days |
Carpeting |
LRP047 |
200 |
45.951 |
LRP047 |
700 |
46.451 |
Naogaon, (Division Office) |
| Deposit Works |
Quotation 10-NRD/2005-2006 (Lot No. 10/03) |
13-Jul-2006 |
15 Days |
Carpeting |
LRP047 |
200 |
45.951 |
LRP047 |
600 |
46.351 |
Naogaon, (Division Office) |
| Revenue |
DPM-N 01-NRD/2012-2013 (Package-10) |
14-Aug-2012 |
7 Days |
Carpeting |
LRP048 |
310 |
47.106 |
LRP048 |
520 |
47.316 |
Naogaon, (Division Office) |
| Deposit Works |
Quotation 10-NRD/2005-2006 (Lot No. 10/03) |
13-Jul-2006 |
15 Days |
Carpeting |
LRP048 |
400 |
47.196 |
LRP048 |
500 |
47.296 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP049 |
0 |
47.809 |
LRP049 |
1000 |
48.809 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation-15-NRD/2005-2006 (Lot No. 15/06) |
7-May-2006 |
15 Days |
Pavement |
LRP049 |
100 |
47.909 |
LRP049 |
300 |
48.109 |
Naogaon, (Division Office) |
| Deposit Works |
Quotation 10-NRD/2005-2006 (Lot No. 10/10) |
8-Jun-2006 |
15 Days |
Road Embankment |
LRP049 |
375 |
48.184 |
LRP049 |
600 |
48.409 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 34-NRD/2005-2006 (Lot No. 34/03) |
13-Jul-2006 |
15 Days |
Pavement |
LRP049 |
400 |
48.209 |
LRP049 |
700 |
48.509 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP050 |
0 |
48.787 |
LRP050 |
1000 |
49.787 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation-15-NRD/2005-2006 (Lot No. 15/06) |
7-May-2006 |
15 Days |
Pavement |
LRP050 |
200 |
48.987 |
LRP050 |
500 |
49.287 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Quotation 10-NRD/2005-2006 (Lot No. 10/10) |
8-Jun-2006 |
15 Days |
Road Embankment |
LRP050 |
400 |
49.187 |
LRP050 |
800 |
49.587 |
Naogaon, (Division Office) |
| Revenue |
Tender 07-NRD/2006-2007 (Lot 07/07) |
1-Feb-2007 |
35 Days |
Carpeting |
LRP050 |
787 |
49.574 |
LRP051 |
784 |
50.568 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP051 |
0 |
49.784 |
LRP051 |
1000 |
50.784 |
Naogaon, (Division Office) |
| Revenue |
DPM-N 01-NRD/2012-2013 (Package-13) |
14-Aug-2012 |
7 Days |
Carpeting |
LRP051 |
230 |
50.014 |
LRP051 |
510 |
50.294 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP052 |
0 |
50.781 |
LRP052 |
1000 |
51.781 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/05) |
21-Jun-2006 |
15 Days |
Pavement |
LRP052 |
200 |
50.981 |
LRP052 |
500 |
51.281 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/05) |
21-Jun-2006 |
15 Days |
Pavement |
LRP053 |
400 |
52.177 |
LRP053 |
600 |
52.377 |
Naogaon, (Division Office) |
| Revenue |
LTM 01-NRD/2010-2011 (Package-05) |
14-Oct-2010 |
15 Days |
Carpeting |
LRP053 |
900 |
52.677 |
LRP054 |
300 |
53.058 |
Naogaon, (Division Office) |
| Revenue |
DPM-N 01-NRD/2012-2013 (Package-12) |
14-Aug-2012 |
7 Days |
Carpeting |
LRP056 |
240 |
55.013 |
LRP056 |
360 |
55.133 |
Naogaon, (Division Office) |
| Revenue |
LTM 08-NRD/2011-2012 (Package-02) |
3-Jun-2012 |
40 Days |
Carpeting |
LRP055 |
1400 |
55.187 |
LRP055 |
1600 |
55.387 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 24-NRD/2005-2006 (Lot No. 24/12) |
15-Aug-2006 |
15 Days |
Road Embankment |
LRP054 |
3000 |
55.758 |
LRP067 |
3000 |
68.705 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 07-NRD/2006-2007 (Lot No. 07/04) |
16-Jan-2007 |
35 Days |
Pavement |
LRP058 |
100 |
56.861 |
LRP058 |
500 |
57.261 |
Naogaon, (Division Office) |
| Revenue |
DPM 01-NRD/2010-2011 (Package-06) |
12-Jan-2011 |
7 Days |
Carpeting |
LRP058 |
239 |
57 |
LRP058 |
400 |
57.161 |
Naogaon, (Division Office) |
| Revenue |
LTM 06-NRD/2011-2012 (Package-02) |
21-May-2012 |
40 Days |
Carpeting |
LRP057 |
1700 |
57.476 |
LRP058 |
1500 |
58.261 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 15-NRD/2005-2006 (Lot No. 15/02) |
21-Jun-2006 |
15 Days |
Pavement |
LRP060 |
100 |
58.868 |
LRP060 |
400 |
59.168 |
Naogaon, (Division Office) |
| Revenue |
DPM 01-NRD/2010-2011 (Package-07) |
12-Jan-2011 |
7 Days |
Carpeting |
LRP060 |
232 |
59 |
LRP061 |
261 |
60 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Restricted 16-NRD/2004-2005 (Lot No. 16/07) |
26-Jun-2005 |
7 Days |
Pavement |
LRP060 |
400 |
59.168 |
LRP060 |
700 |
59.468 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/08) |
12-Feb-2006 |
15 Days |
Pavement |
LRP061 |
200 |
59.939 |
LRP061 |
400 |
60.139 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 15-NRD/2005-2006 (Lot No. 15/02) |
21-Jun-2006 |
15 Days |
Pavement |
LRP061 |
200 |
59.939 |
LRP061 |
500 |
60.239 |
Naogaon, (Division Office) |
| Revenue |
Quotation-N 01-NRD/2012-2013 (Package-01) |
27-Aug-2012 |
7 Days |
Carpeting |
LRP061 |
261 |
60 |
LRP063 |
283 |
62 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/08) |
12-Feb-2006 |
15 Days |
Pavement |
LRP062 |
400 |
61.134 |
LRP062 |
700 |
61.434 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP064 |
0 |
62.716 |
LRP064 |
1000 |
63.716 |
Naogaon, (Division Office) |
| Revenue |
Quotation 06-NRD/2010-2011 (Package-07) |
23-Jan-2011 |
7 Days |
Carpeting |
LRP064 |
400 |
63.116 |
LRP064 |
800 |
63.516 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP065 |
0 |
63.714 |
LRP065 |
1000 |
64.714 |
Naogaon, (Division Office) |
| Deposit Works |
Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP065 |
0 |
63.714 |
LRP065 |
1000 |
64.714 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17-NRD/2005-2006 (Lot No. 17/08) |
8-Jun-2006 |
15 Days |
Pavement |
LRP065 |
200 |
63.914 |
LRP065 |
400 |
64.114 |
Naogaon, (Division Office) |
| Revenue |
Tender 07-NRD/2006-2007 (Lot 07/05) |
30-Jan-2007 |
35 Days |
Carpeting |
LRP065 |
286 |
64 |
LRP065 |
550 |
64.264 |
Naogaon, (Division Office) |
| Revenue |
DPM 01-NRD/2010-2011 (Package-09) |
12-Jan-2011 |
7 Days |
Carpeting |
LRP066 |
0 |
64.713 |
LRP067 |
0 |
65.705 |
Naogaon, (Division Office) |
| Revenue |
Quotation 01-NRD/2011-2012 (Package-03) |
8-Sep-2011 |
7 Days |
Carpeting |
LRP064 |
2000 |
64.716 |
LRP064 |
2500 |
65.216 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
D-Tender 38-NRD/2005-2006 (Lot No. 38/13) |
13-Aug-2006 |
15 Days |
Pavement |
LRP066 |
100 |
64.813 |
LRP066 |
300 |
65.013 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Tender 07-NRD/2006-2007 (Lot No. 07/06) |
16-Jan-2007 |
35 Days |
Pavement |
LRP066 |
400 |
65.113 |
LRP066 |
800 |
65.513 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17-NRD/2005-2006 (Lot No. 17/08) |
8-Jun-2006 |
15 Days |
Pavement |
LRP066 |
400 |
65.113 |
LRP066 |
600 |
65.313 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17 NRD/2005-2006(Lot No. 17/06) |
15-Jun-2006 |
15 Days |
Pavement |
LRP065 |
2000 |
65.714 |
LRP065 |
2200 |
65.914 |
Naogaon, (Division Office) |
| Revenue |
PMP-03/2011-2012 (Package PMP-03/2011-12/05/Overlay) |
19-Feb-2012 |
456 Days |
Overlay |
LRP034 |
33280 |
66.067 |
LRP034 |
67208 |
99.995 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17-NRD/2005-2006 (Lot No. 17/08) |
8-Jun-2006 |
15 Days |
Pavement |
LRP067 |
400 |
66.105 |
LRP067 |
700 |
66.405 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17 NRD/2005-2006(Lot No. 17/06) |
15-Jun-2006 |
15 Days |
Pavement |
LRP066 |
2050 |
66.763 |
LRP066 |
2350 |
67.063 |
Naogaon, (Division Office) |
| Revenue |
LTM 04-NRD/2011-2012 (Package-03) |
24-Apr-2012 |
40 Days |
Road Embankment |
LRP067 |
1450 |
67.155 |
LRP067 |
2440 |
68.145 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17-NRD/2005-2006 (Lot No. 17/07) |
1-Jun-2006 |
15 Days |
Pavement |
LRP067 |
2000 |
67.705 |
LRP067 |
4000 |
69.705 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 17-NRD/2005-2006 (Lot No. 17/07) |
1-Jun-2006 |
15 Days |
Pavement |
LRP067 |
3000 |
68.705 |
LRP067 |
5000 |
70.705 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 20-NRD/2005-2006 (Lot No. 20/05) |
16-Jul-2006 |
15 Days |
Pavement |
LRP035 |
35000 |
68.786 |
LRP035 |
45000 |
78.786 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 10-NRD/2005-2006 (Lot No. 10/01) |
27-Apr-2006 |
15 Days |
Pavement |
LRP038 |
38400 |
75.181 |
LRP038 |
38600 |
75.381 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 10-NRD/2005-2006 (Lot No. 10/01) |
27-Apr-2006 |
15 Days |
Overlay |
LRP038 |
38400 |
75.181 |
LRP038 |
38600 |
75.381 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 10-NRD/2005-2006 (Lot No. 10/01) |
27-Apr-2006 |
15 Days |
Pavement |
LRP039 |
39100 |
76.868 |
LRP039 |
39200 |
76.968 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP056 |
56000 |
110.773 |
LRP056 |
57000 |
111.773 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP057 |
57000 |
112.776 |
LRP057 |
58000 |
113.776 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP058 |
58000 |
114.761 |
LRP058 |
59000 |
115.761 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP059 |
59000 |
116.747 |
LRP059 |
60000 |
117.747 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP060 |
60000 |
118.768 |
LRP060 |
61000 |
119.768 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP061 |
61000 |
120.739 |
LRP061 |
62000 |
121.739 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP062 |
62000 |
122.734 |
LRP062 |
63000 |
123.734 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 13-NRD/2005-2006 (Lot No. 13/02) |
12-Jun-2006 |
15 Days |
Pavement |
LRP063 |
63000 |
124.717 |
LRP063 |
64000 |
125.717 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 10-NRD/2005-2006 (Lot No. 10/02) |
27-Apr-2006 |
15 Days |
Pavement |
LRP064 |
64200 |
126.916 |
LRP064 |
64400 |
127.116 |
Naogaon, (Division Office) |
| Revenue Periodic Roads |
Quotation 10-NRD/2005-2006 (Lot No. 10/02) |
27-Apr-2006 |
15 Days |
Pavement |
LRP065 |
65300 |
129.014 |
LRP065 |
65700 |
129.414 |
Naogaon, (Division Office) |