List of ongoing works on the road ( Z1601 )
Fund Source   Contract no.   St. Date   Duration   Type of work  Start location End location  Res.Division 
           LRP   Offset  Chainage      LRP   Offset  Chainage      
 Development  OTM/Dev/Khag/CtgZone/CZ-16/2016-2017 (Tender ID: 88365)  9-Jul-2017  1330 Days  Road Rehablitation  LRPS  0 0     LRPE  0 13.81     Khagrachari, (Division Office) 
 Development  244/E.E./K.R.D./2007-2008.  12-Jun-2008  20 Days  Carpeting  LRPS  0 0     LRP005  0 5     Khagrachari, (Division Office) 
 Development  116/E.E./K.R.D./2007-2008.  12-Jun-2008  20 Days  Pavement  LRPS  0 0     LRP012  0 11.883     Khagrachari, (Division Office) 
 Development  108/E.E./K.R.D./2007-2008.  12-Jun-2008  15 Days  Carpeting  LRPS  0 0     LRP005  0 5     Khagrachari, (Division Office) 
 Development  07/E.E./K.R.D./2007-2008  19-Sep-2007  60 Days  Road Embankment  LRPS  390 0.39     LRPS  408 0.408     Khagrachari, (Division Office) 
 Development  67/E.E./K.R.D/2007-2008.  12-Jun-2008  20 Days  Carpeting  LRP005  0 5     LRP006  0 5.957     Khagrachari, (Division Office) 
 Development  48/E.E./K.R.D./2006-2007  8-Mar-2007  20 Days  Road Rehablitation  LRP005  3 5.003     LRP006  6 5.963     Khagrachari, (Division Office) 
 Development  121/E.E./K.R.D./2007-2008.  12-Jun-2008  20 Days  Pavement  LRP005  3 5.003     LRP006  3 5.96     Khagrachari, (Division Office) 
 Development  47/E.E./K.R.D/2006-2007  8-Mar-2007  30 Days  Road Rehablitation  LRP008  9 7.955     LRP010  10 9.89     Khagrachari, (Division Office) 
 Development  28/E.E./K.R.D./2006-2007.  17-Dec-2006  20 Days  Road Rehablitation  LRP010  10 9.89     LRP012  12 11.895     Khagrachari, (Division Office) 
 Development  244/E.E./K.R.D./2007-2008.  12-Jun-2008  20 Days  Carpeting  LRP012  0 11.883     LRPE  0 13.81     Khagrachari, (Division Office) 
 Development  107/E.E./K.R.D./2007-2008.  12-Jun-2008  30 Days  Carpeting  LRP012  0 11.883     LRPE  0 13.81     Khagrachari, (Division Office) 
 
 Note: The on going work list is gathered from Central Management System (CMS) running in the field divisions and the information is updated once in a month at RHD head office. This information is largely depended on how the work is defined in CMS and will not include any contract that is not properly defined by field division