List of ongoing works on the road ( Z1811 )
Fund Source   Contract no.   St. Date   Duration   Type of work  Start location End location  Res.Division 
           LRP   Offset  Chainage      LRP   Offset  Chainage      
 Revenue  OTM-11/EE/BRD/2008-09 (Lot No. 4/2)  4-Feb-2009  20 Days  Road Rehablitation  LRP002e  3 1.709     LRP024  0 23     Bandarban, (Division Office) 
 Revenue Others  RFQ No.5/EE/BRD/2007-08 (Lot No.3/2)  25-Nov-2007  8 Days  Pavement  LRP003  3 1.997     LRP020  0 18.949     Bandarban, (Division Office) 
 Revenue  OTM-16/EE/BRD/2008-09 (Lot No.3/4)  10-Feb-2009  30 Days  Carpeting  LRP003  420 2.414     LRP003  432 2.426     Bandarban, (Division Office) 
 Revenue Others  OTM/46/EE/BRD/2007-08 (Lot No. 8/2)  14-May-2008  40 Days  Carpeting  LRP003  4500 6.494     LRP013  14500 26.448     Bandarban, (Division Office) 
 Revenue Others  OTM-21/EE/BRD/2007-2008 (Lot no.5/11)  24-Mar-2008  30 Days  Carpeting  LRP008  1245 8.28     LRP008  2000 9.035     Bandarban, (Division Office) 
 Revenue Others  RTM-19/EE/BRD/2007-08 (Lot No.12/1)  17-Apr-2008  15 Days  Road Rehablitation  LRP005  5800 9.794     LRP005  5815 9.809     Bandarban, (Division Office) 
 Revenue Others  OTM-01/EE/BRD/2007-08 (Lot No.1/4)  5-Feb-2008  25 Days  Carpeting  LRP013  1330 13.278     LRP013  1345 13.293     Bandarban, (Division Office) 
 Revenue  OTM-29/EE/BRD/2008-09 (Lot No.6/4)  23-Apr-2009  30 Days  Road Embankment  LRP019  900 18.849     LRP019  2000 19.949     Bandarban, (Division Office) 
 Revenue  OTM-33/EE/BRD/2008-09 (Lot No. 6/5)  4-May-2009  25 Days  Road Embankment  LRP020  230 19.179     LRP020  245 19.194     Bandarban, (Division Office) 
 Revenue  OTM-29/EE/BRD/2008-09 (Lot No.6/4)  23-Apr-2009  30 Days  Road Embankment  LRP020  760 19.709     LRP020  865 19.814     Bandarban, (Division Office) 
 Revenue  OTM-29/EE/BRD/2008-09 (Lot No.6/4)  23-Apr-2009  30 Days  Road Embankment  LRP020  2000 20.949     LRP020  2050 20.999     Bandarban, (Division Office) 
 Revenue Others  OTM/45/EE/BRD/2007-08(Lot No. 8/1)  30-Apr-2008  40 Days  Carpeting  LRP016  15000 29.927     LRP017  17000 32.96     Bandarban, (Division Office) 
 Revenue Others  OTM/38/EE/BRD/2007-08 (Lot No. 8/3)  23-Apr-2008  30 Days  Road Embankment  LRP017  17708 33.668     LRP017  17720 33.68     Bandarban, (Division Office) 
 Revenue Others  OTM-20/EE/BRD/2007-08 (Lot No. 5/4)  24-Mar-2008  40 Days  Carpeting  LRP019  18000 35.949     LRP019  20000 37.949     Bandarban, (Division Office) 
 Revenue Others  OTM/19/EE/BRD/2007-08 (Lot No. 5/1)  24-Mar-2008  35 Days  Carpeting  LRP020  20000 38.949     LRP020  21000 39.949     Bandarban, (Division Office) 
 Revenue Others  OTM/39/EE/BRD/2007-08 (Lot No. 5/2)  30-Mar-2008  30 Days  Carpeting  LRP020  21000 39.949     LRP020  22000 40.949     Bandarban, (Division Office) 
 Revenue Others  OTM-50/EE/BRD/2007-08 (Lot No.5/3)  27-May-2008  35 Days  Carpeting  LRP020  22000 40.949     LRP020  23000 41.949     Bandarban, (Division Office) 
 
 Note: The on going work list is gathered from Central Management System (CMS) running in the field divisions and the information is updated once in a month at RHD head office. This information is largely depended on how the work is defined in CMS and will not include any contract that is not properly defined by field division