The RMMS Database upgradation is going on.
***The information being shown here is under review.***
   Search by location      Home  
   Road Maintenance Card Search by Road name     
  

 
 
List of ongoing works on the road ( Z5802 )
Fund Source   Contract no.   St. Date   Duration   Type of work  Start location End location  Res.Division 
           LRP   Offset  Chainage      LRP   Offset  Chainage      
 Development  07/SE/DRC/2010-2011  25-Apr-2011  180 Days  Carpeting  LRPS  800 0.8     LRP001  100 1.1     Dinajpur, (Division Office) 
 Development  07/SE/DRC/2010-2011  25-Apr-2011  180 Days  Carpeting  LRP001  500 1.5     LRP002  13 2     Dinajpur, (Division Office) 
 Revenue  10/e-GP/RHD/EE/DRD/2016-2017  6-Dec-2016  30 Days  Carpeting  LRPS  2200 2.2     LRPS  3650 3.65     Dinajpur, (Division Office) 
 Development  07/SE/DRC/2010-2011  25-Apr-2011  180 Days  Carpeting  LRP002  213 2.2     LRP002  863 2.85     Dinajpur, (Division Office) 
 Development  07/SE/DRC/2010-2011  25-Apr-2011  180 Days  Carpeting  LRP002  1263 3.25     LRP004  42 4     Dinajpur, (Division Office) 
 Revenue  08/EE/DRD/2009-2010(04)  29-Mar-2010  30 Days  Carpeting  LRP004  692 4.65     LRP004  1342 5.3     Dinajpur, (Division Office) 
 Revenue  08/EE/DRD/2009-2010(04)  29-Mar-2010  30 Days  Carpeting  LRP006  996 6.9     LRP007  148 7.15     Dinajpur, (Division Office) 
 Development  02/EE/DRD(Ph)/2005-2006. Lot No. 03 (Three)  18-Jun-2006  195 Days  Pavement  LRP007  220 7.222     LRP007  1647 8.649     Dinajpur, (Division Office) 
 Revenue  DPM No- 26/EE/DRD/2015-16  5-Jun-2016  5 Days  Carpeting  LRP008  204 8.1     LRP010  0 9.863     Dinajpur, (Division Office) 
 Revenue  08/EE/DRD/2009-2010(04)  29-Mar-2010  30 Days  Carpeting  LRP008  704 8.6     LRP008  904 8.8     Dinajpur, (Division Office) 
 Development  02/EE/DRD(Ph)/2005-2006. Lot No. 03 (Three)  18-Jun-2006  195 Days  Pavement  LRP008  820 8.716     LRP008  987 8.883     Dinajpur, (Division Office) 
 Revenue  25/e-GP/RHD/EE/DRD/2018-2019.  18-Feb-2019  30 Days  Carpeting  LRP008  910 8.8     LRP009  690 9.58     Dinajpur, (Division Office) 
 Development  07/EE/DRD/2007-08  25-Mar-2008  30 Days  Carpeting  LRP008  986 8.882     LRP009  810 9.701     Dinajpur, (Division Office) 
 Revenue  DPM No.-06/SDE/Phul/2011-2012  22-Jun-2012  7 Days  Road Embankment  LRP010  0 9.863     LRP010  500 10.363     Dinajpur, (Division Office) 
 Revenue  DPM No. 07/EE/DRD/2016-17  11-Dec-2016  5 Days  Road Embankment  LRP010  320 10.2     LRP010  720 10.6     Dinajpur, (Division Office) 
 Revenue  08/EE/DRD/2009-2010(04)  29-Mar-2010  30 Days  Carpeting  LRP010  437 10.3     LRP010  837 10.7     Dinajpur, (Division Office) 
 Revenue  25/e-GP/RHD/EE/DRD/2018-2019.  18-Feb-2019  30 Days  Carpeting  LRP010  620 10.5     LRPE  0 13.24     Dinajpur, (Division Office) 
 Revenue  DPM No. 07/EE/DRD/2016-17  11-Dec-2016  5 Days  Road Embankment  LRP010  720 10.6     LRP010  1720 11.6     Dinajpur, (Division Office) 
 Revenue  08/EE/DRD/2009-2010(04)  29-Mar-2010  30 Days  Carpeting  LRP010  1937 11.8     LRP010  2237 12.1     Dinajpur, (Division Office) 
 Revenue Periodic Roads  18/e-GP/RHD/EE/DRD/2015-2016  23-Dec-2015  30 Days  Surfacing  LRP010  2500 12.38     LRP010  3000 12.88     Dinajpur, (Division Office) 
 
 Note: The on going work list is gathered from Central Management System (CMS) running in the field divisions and the information is updated once in a month at RHD head office. This information is largely depended on how the work is defined in CMS and will not include any contract that is not properly defined by field division