| List of ongoing works on the road ( Z5802 ) |
Fund Source  |
Contract no.  |
St. Date  |
Duration  |
Type of work  |
Start location |
End location |
Res.Division  |
| |
|
|
|
|
LRP  |
Offset  |
Chainage |
LRP  |
Offset  |
Chainage |
|
| Development |
07/SE/DRC/2010-2011 |
25-Apr-2011 |
180 Days |
Carpeting |
LRPS |
800 |
0.8 |
LRP001 |
100 |
1.1 |
Dinajpur, (Division Office) |
| Development |
07/SE/DRC/2010-2011 |
25-Apr-2011 |
180 Days |
Carpeting |
LRP001 |
500 |
1.5 |
LRP002 |
13 |
2 |
Dinajpur, (Division Office) |
| Revenue |
10/e-GP/RHD/EE/DRD/2016-2017 |
6-Dec-2016 |
30 Days |
Carpeting |
LRPS |
2200 |
2.2 |
LRPS |
3650 |
3.65 |
Dinajpur, (Division Office) |
| Development |
07/SE/DRC/2010-2011 |
25-Apr-2011 |
180 Days |
Carpeting |
LRP002 |
213 |
2.2 |
LRP002 |
863 |
2.85 |
Dinajpur, (Division Office) |
| Development |
07/SE/DRC/2010-2011 |
25-Apr-2011 |
180 Days |
Carpeting |
LRP002 |
1263 |
3.25 |
LRP004 |
42 |
4 |
Dinajpur, (Division Office) |
| Revenue |
08/EE/DRD/2009-2010(04) |
29-Mar-2010 |
30 Days |
Carpeting |
LRP004 |
692 |
4.65 |
LRP004 |
1342 |
5.3 |
Dinajpur, (Division Office) |
| Revenue |
08/EE/DRD/2009-2010(04) |
29-Mar-2010 |
30 Days |
Carpeting |
LRP006 |
996 |
6.9 |
LRP007 |
148 |
7.15 |
Dinajpur, (Division Office) |
| Development |
02/EE/DRD(Ph)/2005-2006. Lot No. 03 (Three) |
18-Jun-2006 |
195 Days |
Pavement |
LRP007 |
220 |
7.222 |
LRP007 |
1647 |
8.649 |
Dinajpur, (Division Office) |
| Revenue |
DPM No- 26/EE/DRD/2015-16 |
5-Jun-2016 |
5 Days |
Carpeting |
LRP008 |
204 |
8.1 |
LRP010 |
0 |
9.863 |
Dinajpur, (Division Office) |
| Revenue |
08/EE/DRD/2009-2010(04) |
29-Mar-2010 |
30 Days |
Carpeting |
LRP008 |
704 |
8.6 |
LRP008 |
904 |
8.8 |
Dinajpur, (Division Office) |
| Development |
02/EE/DRD(Ph)/2005-2006. Lot No. 03 (Three) |
18-Jun-2006 |
195 Days |
Pavement |
LRP008 |
820 |
8.716 |
LRP008 |
987 |
8.883 |
Dinajpur, (Division Office) |
| Revenue |
25/e-GP/RHD/EE/DRD/2018-2019. |
18-Feb-2019 |
30 Days |
Carpeting |
LRP008 |
910 |
8.8 |
LRP009 |
690 |
9.58 |
Dinajpur, (Division Office) |
| Development |
07/EE/DRD/2007-08 |
25-Mar-2008 |
30 Days |
Carpeting |
LRP008 |
986 |
8.882 |
LRP009 |
810 |
9.701 |
Dinajpur, (Division Office) |
| Revenue |
DPM No.-06/SDE/Phul/2011-2012 |
22-Jun-2012 |
7 Days |
Road Embankment |
LRP010 |
0 |
9.863 |
LRP010 |
500 |
10.363 |
Dinajpur, (Division Office) |
| Revenue |
DPM No. 07/EE/DRD/2016-17 |
11-Dec-2016 |
5 Days |
Road Embankment |
LRP010 |
320 |
10.2 |
LRP010 |
720 |
10.6 |
Dinajpur, (Division Office) |
| Revenue |
08/EE/DRD/2009-2010(04) |
29-Mar-2010 |
30 Days |
Carpeting |
LRP010 |
437 |
10.3 |
LRP010 |
837 |
10.7 |
Dinajpur, (Division Office) |
| Revenue |
25/e-GP/RHD/EE/DRD/2018-2019. |
18-Feb-2019 |
30 Days |
Carpeting |
LRP010 |
620 |
10.5 |
LRPE |
0 |
13.24 |
Dinajpur, (Division Office) |
| Revenue |
DPM No. 07/EE/DRD/2016-17 |
11-Dec-2016 |
5 Days |
Road Embankment |
LRP010 |
720 |
10.6 |
LRP010 |
1720 |
11.6 |
Dinajpur, (Division Office) |
| Revenue |
08/EE/DRD/2009-2010(04) |
29-Mar-2010 |
30 Days |
Carpeting |
LRP010 |
1937 |
11.8 |
LRP010 |
2237 |
12.1 |
Dinajpur, (Division Office) |
| Revenue Periodic Roads |
18/e-GP/RHD/EE/DRD/2015-2016 |
23-Dec-2015 |
30 Days |
Surfacing |
LRP010 |
2500 |
12.38 |
LRP010 |
3000 |
12.88 |
Dinajpur, (Division Office) |